Nevada 811 rules

In Nevada you call USA North 811: at least 2 working days before excavation or demolition is scheduled to commence.

Advance notice before digging
At least 2 working days before excavation or demolition is scheduled to commence.
Farthest ahead you can call
Not more than 28 calendar days.
How long the ticket or marks last
Not confirmed in the law we read. Ask USA North 811.
Tolerance zone (hand dig inside it)
Not more than 24 inches on either side of the exterior surface of the installation.
White lining (premarking)
Yes (reasonable effort to mark proposed area with white paint, flags, stakes, whiskers or agreed method).
The law
NRS 455.080-455.180 (455.110); NAC 455.

Call 811 from anywhere in Nevada to reach USA North 811, or file online at usanorth811.org.

Running several digs at once?

TrackOver keeps each ticket number, markout date and expiry on the job it belongs to, and warns before a ticket runs out, so the crew in the hole isn't digging on a dead ticket.

811 ticket trackingFind dig work on the board

Where this comes from

Checked September 24, 2026 against the state's own statute or rule text. Rules change; confirm with the center before a big job.

Other states

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaFloridaGeorgiaHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming