Montana 811 rules
In Montana you call Montana 811: call before digging; owners must mark within 2 business days (5 for engineering locates). Ticket life: work must be completed within 30 days of notification; if no excavation within 30 days of marking, request re-mark (3rd request at excavator's cost).
Good to know: Work has to be done within 30 days of the notice. A third re-mark with no digging is at your cost.
Call 811 from anywhere in Montana to reach Montana 811, or file online at montana811.org.
TrackOver keeps each ticket number, markout date and expiry on the job it belongs to, and warns before a ticket runs out, so the crew in the hole isn't digging on a dead ticket.
Where this comes from
Checked September 24, 2026 against the state's own statute or rule text. Rules change; confirm with the center before a big job.