In Florida you call Sunshine 811: not less than 2 full business days before excavation or demolition (10 business days for underwater excavation). Ticket life: 30 calendar days; work continuing past that needs a subsequent notice.

Advance notice before digging
Not less than 2 full business days before excavation or demolition (10 business days for underwater excavation).
Farthest ahead you can call
Not confirmed in the law we read. Ask Sunshine 811.
How long the ticket or marks last
30 calendar days; work continuing past that needs a subsequent notice.
Tolerance zone (hand dig inside it)
24 inches from the outer edge of either side of the marked facility.
White lining (premarking)
Yes (premark with white paint, flags or stakes, unless it would interfere with traffic/pedestrian control).
The law
Fla. Stat. ch. 556 (556.102(15), 556.105, 556.114).

Good to know: Underwater digs need 10 business days' notice.

Call 811 from anywhere in Florida to reach Sunshine 811, or file online at sunshine811.com.

Running several digs at once?

TrackOver keeps each ticket number, markout date and expiry on the job it belongs to, and warns before a ticket runs out, so the crew in the hole isn't digging on a dead ticket.

811 ticket trackingFind dig work on the board

Where this comes from

Checked September 24, 2026 against the state's own statute or rule text. Rules change; confirm with the center before a big job.

Other states

AlabamaAlaskaArizonaArkansasCaliforniaColoradoConnecticutDelawareDistrict of ColumbiaGeorgiaHawaiiIdahoIllinoisIndianaIowaKansasKentuckyLouisianaMaineMarylandMassachusettsMichiganMinnesotaMississippiMissouriMontanaNebraskaNevadaNew HampshireNew JerseyNew MexicoNew YorkNorth CarolinaNorth DakotaOhioOklahomaOregonPennsylvaniaRhode IslandSouth CarolinaSouth DakotaTennesseeTexasUtahVermontVirginiaWashingtonWest VirginiaWisconsinWyoming