Excavator production calculator

Yards per hour and the hours and days to dig, from bucket size, cycle time and swell.

The dig
98.2
bank yd³ per hour
122.7
loose yd³ per hour
5.1
hours to dig
0.64
days to dig

Cycles per hour = 3,600 / cycle seconds. Loose yd³ per hour = bucket x fill % x cycles per hour x working minutes / 60. Bank yd³ per hour = loose / (1 + swell %). Hours = yd³ to dig / bank yd³ per hour.

An estimate from the numbers you type, not a machine rating. Cycle time, fill and swell change with the soil, the depth and the operator, so time your own machine and use your own ground.

More free calculators:

Turn this number into an estimate
TrackOver turns it into the estimate, the schedule and the invoice. 7-day free trial, no card needed.
Try TrackOver freeSee it first, no signup
How do you figure excavator production in yards per hour? Divide 3,600 seconds by the cycle time to get cycles per hour. Multiply by the bucket size, by how full the bucket really is, and by the working minutes in the hour divided by 60. That is loose yards per hour. Divide by 1 plus the swell to get bank yards per hour, which is the number to compare against the dirt in the ground.

When to use it

Use it when you are bidding a dig and need to know how many hours or days the excavator will be on the job, or when you want to check that a crew's pace matches the quote.

How to measure on site

  1. Find the yards to dig in the ground (bank yards). The trench, pond dig or dirt calculator will give you that from the length, width and depth.
  2. Use the bucket size on the machine's spec plate, and watch a few buckets to see how full they come up.
  3. Time five or six full cycles with a stopwatch and average them. Use the soil's swell from your own experience or the soil report.
Worked example: a 1 yd³ bucket digging 500 bank yd³
  • Cycles per hour: 3,600 / 22 seconds = 163.6.
  • Loose yards per hour: 1 x 90% x 163.6 x (50 / 60) = 122.7 yd³.
  • Bank yards per hour: 122.7 / (1 + 25%) = 98.2 yd³.
  • Hours to dig: 500 / 98.2 = 5.1 hours, about 0.64 of an 8 hour day.

Common questions

How do you figure excavator production in yards per hour?

Divide 3,600 seconds by the cycle time to get cycles per hour. Multiply by the bucket size, by how full the bucket really is, and by the working minutes in the hour divided by 60. That is loose yards per hour. Divide by 1 plus the swell to get bank yards per hour, which is the number to compare against the dirt in the ground.

What is a normal cycle time for an excavator?

It depends on the machine, the soil, how deep you dig and how far you swing. Time a few full cycles on your own machine with a phone stopwatch, from bucket in the dirt to bucket back in the dirt, and use the average. The default on this page is a starting point, not a spec.

Why use 50 minutes in an hour?

Real hours include waiting on trucks, moving the machine, cleaning up and breaks, so the machine does not dig for all 60 minutes. The default is 50 and the box is yours to change. If a truck is always waiting on you, use a higher number. If you are sloping and trimming a lot, use a lower one.

What is the difference between bank and loose yards?

Bank yards are the dirt in the ground. Once it is dug it fluffs up, so the same dirt takes more room in the bucket and the truck. Those are loose yards. The bucket moves loose yards, so the tool divides by the swell to tell you how many bank yards you cleared.

How much does soil swell when you dig it?

It varies by soil. Sand and gravel swell less than clay and rock. The default here is 25 percent, and you should change it to the number you use for your ground or what your geotechnical report says.

How many days will the dig take?

Hours to dig is the bank yards divided by bank yards per hour, and days is those hours divided by the hours you work in a day. Add time for trucks, shoring, utilities in the way and weather. This is the digging time only.

Running an excavation crew?

TrackOver keeps the estimate, the materials, the crew schedule and the job photos in one place, from the first quote to the final invoice.

Try TrackOver free

7-day free trial, no card needed. See it in 2 minutes

Start your trial with your trade set up:

Want the details first? See how TrackOver runs the job for Excavation, Grading & Clearing and Trucking & Hauling.