Cut and fill calculator
Cut, fill and net import or export in bank cubic yards, then loose yards and truckloads to haul. Use the average end area method for a road or long pad, or four corner grades for a building pad.
Save the numbers to a job, add your price and send the estimate. The crew's hours and photos land on the same job.
- Volume between two stations = (A1 + A2) / 2 x spacing, in ft³. Cut and fill are averaged separately.
- Cubic yards = ft³ / 27.
- Net = cut - fill. Positive is export, negative is import.
- Loose yards = net x (1 + swell / 100). Truckloads = loose yards / truck size, rounded up.
Bank yards, no compaction allowance. Add your own for fill that gets packed.
How do you calculate cut and fill? For a road or long pad, take the cut area and fill area at each station, average the two ends of every segment and multiply by the station spacing. That is the average end area method: volume = (A1 + A2) / 2 x distance, in cubic feet, divided by 27 for cubic yards. Cut is the dirt you dig out, fill is the dirt you place, and net = cut minus fill.
Common questions
For a road or long pad, take the cut area and fill area at each station, average the two ends of every segment and multiply by the station spacing. That is the average end area method: volume = (A1 + A2) / 2 x distance, in cubic feet, divided by 27 for cubic yards. Cut is the dirt you dig out, fill is the dirt you place, and net = cut minus fill.
It treats the ground between two stations as a solid whose volume is the mean of the two cross-section areas times the distance between them. It is the usual hand method for roads and trenches. It runs a little high where the sections change shape fast, so use closer stations there.
Use the pad tab. Enter the pad length and width and the existing and finished grade at the four corners. Each corner's cut or fill is existing minus finished. If every corner is cut or every corner is fill, the volume is area x the sum of the corner depths / 4. If the pad is part cut and part fill, the calculator splits it along the zero line.
Net = cut minus fill in bank yards. A positive net is dirt left over, so you export it and haul it off. A negative net means you are short, so you import fill. Zero means the site balances.
Loose yards = bank yards x (1 + swell percent / 100). Truckloads = loose yards divided by your truck size, rounded up. The swell starts at the same 25 percent default as the trench calculator and the truck at 16 yards. Both are defaults only, so type in your own.
No. The numbers are bank yards. Fill packed in place can take more than a bank yard of dirt per yard of fill, depending on the soil and the spec. Add your own allowance to the fill, or get it from your geotechnical report or earthwork spec.