Truck loads
How many dump truck loads will my dig take?
Convert bank yards to loose yards with swell, divide by the truck's loose capacity, and round up for loads. For how many trucks you need, divide the excavator's loose yards per hour by what one truck hauls in an hour, which depends on its cycle time.
Two questions get mixed together. How many loads leaves the site, and how many trucks do you need so the excavator never waits. The first is a volume question. The second is a time question. Both start with the yards in the ground.
Loads: volume math
- Bank yards. Length x width x depth in feet, divided by 27. See how much spoil comes out of a trench for a worked trench.
- Loose yards. Multiply by 1 plus swell. Dug soil takes more room than it did in the ground. Bank vs loose yards explains it.
- Loads. Divide by the truck's loose capacity and round up. Ask the trucker for that number rather than reading it off the door.
Example, with numbers picked to be easy to check: 200 bank yards at 25 percent swell is 250 loose yards. A 12 yard truck takes 250 / 12 = 20.8, so 21 loads. The dirt calculator converts yards, tons and loads for any hole shape.
Check the weight too
A truck can hit its legal weight before it is full. Wet soil, clay and rock are heavy, so a 12 yard box of wet clay may be a lighter load by volume than the math says. If you are paid or charged by the load, find out whether the trucker counts full boxes or weight.
Trucks: time math
A truck's cycle is everything it does for one load: load at the dig, drive to the dump, dump and turn around, and drive back. Time one real trip with a phone. Say it comes to 6 minutes to load, 24 minutes round trip and 4 minutes to dump, so 34 minutes.
- Trips per hour: working minutes per hour divided by the cycle. At 50 working minutes, 50 / 34 = about 1.47.
- Yards per truck per hour: 1.47 x 12 = about 17.6 loose yards.
- The excavator puts out, say, 60 loose yards an hour. Trucks needed: 60 / 17.6 = 3.4, so 4.
With 4 trucks the digger sets the pace, so 250 loose yards takes about 250 / 60 = 4.2 hours. With only 3 trucks the haul sets the pace at about 53 yards an hour, which is 4.7 hours, and the excavator waits. The dump truck hauling calculator runs this with your own cycle times, and the excavator production calculator gives the yards per hour for the digger.
Where the cycle time hides
- Distance to the dump. The drive is usually the biggest piece. Double the haul, and you need nearly twice the trucks.
- Waiting at the dig. If trucks stack up, you are paying for idle time. If the digger waits, you have too few trucks.
- Scale and dump lines. Disposal sites with a wait add minutes to every trip.
Plan the haul before the first load
- Settle where the dirt goes and how far it is. A dump that is farther or slower than you assumed changes the truck count more than anything else.
- Time a real round trip on the actual route, at the hour you will be running, not a map estimate.
- Decide the number of trucks from the digger's output, then confirm each truck's loose capacity and legal weight with the hauler.
- Keep every haul ticket. Counting tickets against the loads you planned shows right away if the swell or the cycle was off, so the next bid starts from what happened.
When you are balancing cut and fill
If some of the dirt stays on the job, only the excess leaves. The cut and fill calculator nets cut against fill with swell and shrink, and shows the yards to haul off or bring in, and the loads. Compacted fill takes more bank yards than the finished volume, so check what compaction does to the numbers.
Common questions
How many yards is a dump truck? It depends on the truck. Get the loose capacity from your hauler, and do not assume.
Should I bid by the load or by the hour? Either works if you know the cycle. By the hour covers waiting, and by the load only works if the haul is steady.
What if the trucks cannot keep up? The digger waits, and you pay for an operator and a machine that are not moving dirt. Add a truck, shorten the haul, or slow the digger down so nobody idles.
Excavation crews who track hauling tickets against the job see at closeout what really left the site. TrackOver for excavation contractors keeps the tickets, photos and invoice together.