Trench spoil
How much spoil comes out of a trench?
Multiply length x width x depth in feet and divide by 27 to get bank yards. Multiply by 1 plus the swell to get loose yards. A trench 100 feet long, 3 feet wide and 5 feet deep is 55.6 bank yards, or about 69.4 loose yards at 25 percent swell.
Two numbers describe the same dirt. The hole is measured in bank yards, the way the soil sat in the ground. The pile and the truck are measured in loose yards, after the bucket has broken the soil up and air has worked in. Mix the two up and the pile is always bigger than the bid said it would be.
Step 1: the hole, in bank yards
Length x width x depth gives cubic feet. There are 27 cubic feet in a cubic yard, so divide by 27.
Step 2: swell, in plain terms
Swell is how much bigger the soil gets once it is dug. Swell of 25 percent means one bank yard becomes 1.25 loose yards. Planning figures of 20 to 30 percent are common for ordinary soil, and rock and shot rock swell more. Your own ground, moisture and how you dig move that number, so use what your crews have seen if you have it.
You will also see it written as a swell factor, which is the flip side: bank divided by loose. At 25 percent swell the factor is 1 / 1.25 = 0.80. Loose yards are then bank yards divided by 0.80. Both ways give the same answer. What goes wrong is using a table that is built one way with a formula built the other.
Worked example: 100 feet of trench
- Size: 100 feet long, 3 feet wide, 5 feet deep.
- Cubic feet: 100 x 3 x 5 = 1,500.
- Bank yards: 1,500 / 27 = 55.6.
- Loose yards at 25 percent swell: 55.6 x 1.25 = 69.4. Same thing with the factor: 55.6 / 0.80 = 69.4.
- Truckloads: with a 12 yard truck, 69.4 / 12 = 5.8, so 6 loads. Use your own truck's real capacity, not the number on the door.
If all of it has to leave the site, you are hauling 69.4 yards, not 55.6. That gap of nearly 14 yards is more than a full truck.
What goes back in the trench
Not everything leaves. The pipe takes up room where dirt used to be. Say it is 12 inch outside diameter pipe running the full 100 feet. Its cross section is about 0.785 square feet, so 0.785 x 100 = 78.5 cubic feet, or 2.9 yards. Bedding stone, if you bring it in, takes up room the same way.
In the best case, where the spoil goes back clean and compacts to the density it had before, the leftover is about the volume of the pipe: 2.9 bank yards, roughly 3.6 loose. That is the floor, not the plan. Wet soil, organics, rock and trench width that wandered wider than planned all push it up, and if the native soil is not fit to put back, you haul all of it and buy fill. See spoil vs fill for when it can go back.
What changes the number
- Sloped or benched sides. A trench cut back at the top is wider than the bottom, so a simple length x width x depth box understates the dig. Measure the average width.
- Bell holes, pits and tie-ins. Add them as their own small holes.
- Pavement and base. Saw cut asphalt, concrete and stone base come out as their own material, not as soil.
- Over-dig. A bucket wider than the trench, or a trench that was widened for a trench box, adds yards fast.
The trench calculator gives spoil, bedding and backfill from the trench size, and the dirt calculator converts yards to tons and loads for any hole shape. For a longer look at the two kinds of yard, read bank vs loose yards.
Common questions
Is spoil bank yards or loose yards? The hole is bank yards. The pile and the truck are loose yards. State which one every number in your bid means.
What swell should I use? A range of 20 to 30 percent is a common planning figure for ordinary soil. Use a higher number for rock or heavy clay, and use your own history when you have it.
How many truckloads is 100 feet of trench? For the 3 by 5 foot trench above, about 6 loads of 12 yards if every yard leaves. Fewer if clean spoil goes back in.
Does compacting spoil make it smaller than bank? It can come back close to bank density or a little under, depending on the soil and the compaction. Do not assume the pile shrinks back to the hole size on its own.
Excavation crews who keep dig quantities, hauling tickets and photos on the same job know at closeout what really left the site. TrackOver for excavation contractors is built for that.