Pricing an excavation job
How do you price an excavation job?
Work out the hours first, then cost each piece: machine time, labor, trucking, dump fees, materials and overhead. Add them up, and only then put profit on top as a margin on the price. Pricing from a gut number or a yard rate skips the part that tells you whether the job pays.
Most contractors can tell you what they charged. Far fewer can tell you what the job cost to do, which is the only thing that decides whether a price was good. The method below builds the price in the order the work happens, so each line is something you can check later against the real job.
If you want the site walk and the paperwork side, read how to bid excavation work. This page is the arithmetic.
Step 1: Start with the hours, not the dollars
Everything on a dirt job hangs off how long the machine runs. Figure the yards, then divide by how many yards an hour the machine moves in that ground. The excavator production calculator does this from bucket size, cycle time, fill and swell. Put the machine hours down first because labor, trucking and often the schedule all follow from them.
Remember that you price the dirt in the ground (bank yards) but you haul it loose. Dirt takes up more room once it is dug, so the truck count comes from the larger number. See bank vs loose yards if that is new.
Step 2: Cost each piece
- Machine time. Hours times your cost per hour, with the machine's ownership and running costs in it. The equipment cost per hour calculator builds that rate, and how to calculate equipment cost per hour explains the pieces. A paid-off machine still has a cost.
- Labor. Hours times the loaded rate: wage plus taxes, insurance and benefits. Include the grade hand, the layout, and the time getting set up and cleaned up, not just the hours the bucket is moving.
- Trucking. Count loads, then truck hours. The dump truck hauling calculator shows how many trucks keep the excavator busy and how many loads and hours that adds up to. Our trucking and haul-off pricing guide covers the rest.
- Dump fees and materials. The tipping fee, the stone, the pipe, the fabric. Get a current number for each instead of remembering last year's.
- Mobilization. Moving the machine on and off the site, and any permits or traffic control. It is easy to forget because it is not dirt.
Step 3: Add overhead
Direct costs are what the job burns. Overhead is the office, the insurance, the software, the yard and the owner's truck, all of which keep running between jobs. Spread it across your jobs, either as a share of direct cost or as an amount per machine hour. Figuring overhead and markup walks through how to find your own number. Do not borrow someone else's.
Step 4: Put profit on top, as a margin
Markup is profit as a share of your cost. Margin is profit as a share of the price. They are not the same number, and swapping them is how a job meant to earn 20 percent earns 16.7. The markup and margin calculator shows both side by side from your cost. Pick one to bid with and one to report with, and do not mix them.
A worked example (sample numbers only)
These are plain sample figures to show the shape of the math. They are not rates for any machine, truck or market. A job to dig and haul off 600 bank yards:
- Digging: 600 yards at a sample 40 bank yards an hour is 15 machine hours. At a sample $63 an hour with the operator, that is $945.
- Labor: 15 hours of a grade hand at a sample $38 loaded is $570.
- Mobilization: a sample $300 to move the machine.
- Trucking: 600 bank yards at 25 percent swell is 750 loose yards. In 12-yard trucks that is 63 loads. At about one hour a round trip and a sample $85 an hour per truck, $5,355.
- Dump fees: 750 loose yards at a sample $5 a yard is $3,750.
- Materials: a sample $1,280 of stone and fabric for the base.
Direct cost is $12,200. Add sample overhead at 10 percent of direct cost, $1,220, for a loaded cost of $13,420.
At a 20 percent margin, the price is $13,420 / 0.80 = $16,775, which leaves $3,355 profit. At a 20 percent markup, the price is $13,420 x 1.20 = $16,104. Profit is $2,684, which is only a 16.7 percent margin. Same cost, $671 apart, from one word.
Notice where the money sits. In this sample, trucking and dump fees are over two thirds of the direct cost, and the machine is under a tenth. A bid that fussed over the machine rate and guessed the haul would have missed the point.
Risk is its own line
The build-up prices the job you expect. Rock, water and bad soil are the job you might get. Cover them in writing with unit prices, as in a rock clause, instead of padding every bid and losing the ones you did not need to lose.
Close the loop
After the job, compare each line to what really happened: machine hours, truck hours, loads, dump tickets. The gap is your next bid's correction. That is what job costing is for. A price you never check against the finished job is a guess you repeat.
Common questions
How do you price an excavation job? Estimate the machine hours from the yards and the production rate, cost machine time, labor, trucking, dump fees, materials and mobilization, add overhead, then add profit as a margin on the price.
Should I price by the yard or by the hour? A yard rate is a good check, not a method. Build the price from costs, then divide by the yards to see if it lands near what you normally charge. If it does not, find out why before you send it.
What is the difference between markup and margin? Markup is profit divided by cost. Margin is profit divided by price. A 25 percent markup is a 20 percent margin.
Where do most excavation bids go wrong? Usually the haul: too few loads, too long a round trip, or a dump fee that changed. Count loose yards, not bank yards, and call the dump for the current rate.
Do I charge for a machine that is paid off? Yes. It still burns fuel, wears out and has to be replaced someday.