Excavation cost calculator
Enter the yards, what the machine costs you an hour, how fast it digs, and what trucking and dumping cost a load. See your cost per yard and the job total.
Hours = bank yards / yards per hour. Loads = bank yards x (1 + swell) / truck yards, rounded up. Direct cost = hours x (machine + crew) + loads x (trucking + dump) + other. Total = direct x (1 + overhead). Per yard = total / bank yards. This stops at overhead: put profit on top with the markup and margin calculator.
Every box is yours. The starting numbers are examples to show the math, not prices, rates or averages for any machine, soil or market.
More free calculators:
When to use it
Use it when you are bidding a dig and want your cost per yard and a job total built from your own machine, crew, trucks and overhead.
How to measure on site
- Get the bank yards from the plans, or measure the length, width and depth of the dig in feet.
- Use your own machine cost per hour and a production rate from past jobs in the same soil.
- Get the cost of one truck load and the dump fee for one load from the people who charge you.
- Yards from a box: 60 x 40 x 6 ft / 27 = 533.3 bank yards. This example uses 500.
- Machine hours: 500 / 60 yards an hour = 8.3.
- Machine: 8.3 x $150 = $1,250. Crew: 8.3 x $45 = $375.
- Loose yards: 500 x 1.25 = 625. Loads: 625 / 12 = 53 after rounding up.
- Trucking: 53 x $110 = $5,830. Dump fees: 53 x $20 = $1,060.
- Direct cost: $8,515. Overhead at 15%: $1,277.25. Job total: $9,792.25.
- Cost per yard: $9,792.25 / 500 = $19.58.
Common questions
Work out the yards in the ground. Divide by how many yards the machine digs in an hour to get machine hours. Price the machine and crew for those hours, add trucking and dump fees for each load, add any other costs, then add your overhead. Divide the total by the yards for your cost per yard.
It is the job total divided by the bank yards, which are the yards in the ground. It only means something with a scope behind it: dig only, dig and haul, or finished grade each give a different number. Use this to find your own, not to match someone else's range.
Switch to length, width and depth in feet. The tool multiplies them and divides by 27, the same math as the dirt calculator. Add each part of the dig separately if the shape is not a box.
The equipment cost per hour calculator gives what the machine costs you to own and run. The excavator production calculator gives bank yards per hour from bucket size, cycle time and swell. Your own logs from past jobs are better than either.
By the load. The tool turns bank yards into loose yards with your swell, divides by what your truck carries and rounds up to whole loads. The dump truck hauling calculator shows how many trucks keep the excavator busy. Type the cost of one load and the fee for one load.
No. It stops at overhead, so it is your cost with overhead on it. Put your profit on top with the markup and margin calculator, and keep markup and margin straight.
It is a way to build your own number. The starting figures are examples to show the math, not prices, and nothing here is an industry average. Rock, water, access and a minimum charge can move a real job a long way.
TrackOver keeps the estimate, the machines, the trucks and the job costs in one place, so you can compare what you bid to what the dig really cost.