811 notice period

How many days before you dig do you have to call 811?

It depends on the state, but most want at least two or three working days between your call and the dig, and some also cap how far ahead you can call. New Jersey says three business days, Texas 48 hours not counting weekends and holidays. Check your state's page before you set a start date.

Calling 811 the morning you want to dig is the most common way to lose a day. Every state sets a waiting period so the utilities have time to send a locator, and the count is not the same everywhere. Some states count working days, some count hours, some skip the day you call, and some start the clock the next morning.

What the rules say in a few states

These come from the 811 rules by state data, gathered in September 2026 from each state's law or one-call center. Read your own state's page for the full wording and the source, because rules change.

  • New Jersey: not less than three business days before you begin, and not more than 10 business days ahead.
  • Texas: no later than 48 hours before excavation begins, not counting Saturdays, Sundays and legal holidays. The page lists 14 days as the longest lead time.
  • California: at least two working days and not more than 14 calendar days, not counting the day you call.
  • Florida: not less than two full business days, and 10 business days for underwater excavation.
  • New York: at least two but not more than 10 working days, not including the day of the call.
  • Ohio: at least two working days, not including the day of notification, and the page lists 16 calendar days as the outer limit.
  • Alaska: at least two working days, with 10 to 20 working days for remote areas.

Notice the pattern. There is a minimum wait before you may dig, and in many states a maximum lead time, meaning you can call too early. A ticket called three weeks before a start date may not be good by the time the crew shows up. The state pages for New Jersey, Texas, California and the rest show the exact wording.

Counting the wait without guessing

  1. Find the minimum notice for the state where the dirt is, not where your shop is.
  2. Check whether the day you call counts. Several states say it does not.
  3. Skip weekends and legal holidays if the rule says working or business days.
  4. Count forward to the first day you may dig, and put that date on the schedule, not the day you hope for.

The 811 ticket expiration calculator does this count for a state and call date and also shows when the ticket runs out. It works from the same state data, so it is only as current as that data. Confirm the date with your one-call center when the job is tight.

What white lining is

White lining means marking the dig area in white paint, flags or stakes before the locators come, so they know exactly where you plan to dig. Several states require it when practical, among them California, Florida and Ohio. New Jersey and New York encourage it. A few states ask for it when the site cannot be described clearly on the ticket. Even where it is optional, it is cheap: a locator who can see the work area marks the right lines instead of guessing, and you avoid a second call. The markout colors guide covers what the locators paint back.

Emergencies and after hours

Most states carve out an emergency exception for a real emergency, such as a leak or an outage, and the rule usually still says to notify the center. Do not treat a rush job as an emergency. If the work was scheduled, the waiting period applies.

Common questions

Can I call 811 the same day I dig? Not legally in the states above, because each sets a waiting period of at least two working days or 48 hours.

Can I call too early? In states with a maximum lead time, yes. Calling earlier than the limit can leave you with a ticket that does not cover your start date.

Does Saturday count? Where the rule says working or business days, no. Texas says it excludes Saturdays, Sundays and legal holidays.

What if marks are not there when the wait is up? Do not dig. Call the center back and ask. See how long an 811 ticket is good for for what happens after the marks are in.

Crews with several digs open keep each ticket's number, call date and first dig day on the job. 811 ticket tracking in TrackOver does that, and the crew sees the date before they roll out.

Related

More from the dirt world

TrackOver keeps the as-builts, markout tickets, hours, and job costs this page talks about. Start free, or see how it works.

Keep the job, the photos and the invoice in one place

TrackOver is job tracking for excavation, utility, paving, snow and lawn crews. Try everything free for 7 days.

  • No card to start
  • Cancel any time, no contract
  • Export your data whenever you want