811 ticket life
How long is an 811 ticket good for?
It depends on the state, and in some states there are two clocks: one to start digging and one for how long the marks stay good. Look up your state's rule, write the date on the job the day you get the ticket, and re-call before it lapses, not after.
A ticket is not a permit with one date on it. Depending on where you work, the number you care about is how long you have to start, how long the marks stay valid once you do, or both. Crews get burned when they remember one and assume it is the other.
Find your state's number
Every state sets its own rule, and the wording varies: working days or calendar days, counted from the call or from the next morning, with or without a fixed end date. Don't go by a number somebody told you at a job two states over. The 811 rules by state page lists each state's rule with the law or call center it comes from, and each state has its own page you can open from there. Read it for the state where the dirt is, not the one your shop is in.
What to do before it runs out
- Write the dates down the day the ticket comes in. Ticket number, the day you called, the day marks were done, and the day it lapses. Put them on the job, not in a text thread.
- Look at the end date when you schedule. If the trench won't be open and closed inside the window, plan the re-call into the schedule as a task, not a surprise.
- Keep the marks alive. Where the rule says the ticket holds only while the marks are maintained, paint that rain washed out or a loader scuffed off is a problem even if the date is fine. Photograph the marks when you start.
- Re-call early. New tickets come with their own wait before you can dig. Calling the day before the old one lapses can leave a gap with no valid ticket, so count that wait backwards from your dig date.
- If the job stops, check before you restart. A rain week or a waiting-on-inspection week can eat the window. Treat a restart after a pause as a date check, every time.
When a ticket has lapsed
Stop and re-call. Digging on an expired ticket puts you in the same spot as digging with none: if a line gets hit, the paper doesn't protect you. Don't dig it to finish the day.
Keeping track across several open digs
One ticket is easy to remember. Four open ones, each called on a different day, each expiring on a different day, is where dates get missed. Keep each ticket's number and dates on the job it belongs to, where the crew and the office both see it. That's what 811 ticket software for contractors in TrackOver does, and you can try it free for 7 days with no card.