Rods for a bore

How many rods does a directional bore take?

To reach depth, divide the target depth by the drop per rod (rod length times pitch) and round up. To cover a whole shot, divide its length by the rod length. A 200 foot shot with 10 foot rods is about 20 rods.

Two different questions hide in this one. How many rods does it take to get down to depth at the entry, and how many rods is the whole shot. Plan the first with pitch, the second with length.

Rods to reach depth

Each rod drops the head by rod length times the pitch. Pitch is the grade the locator reads, as a percent.

  • Drop per rod = rod length x pitch percent / 100.
  • Rods to depth = target depth / drop per rod, rounded up.

Example: 10 foot rods at 20 percent pitch, target depth 6 feet. Drop per rod = 10 x 0.20 = 2 feet. Rods = 6 / 2 = 3 rods, about 30 feet of surface run. With 15 foot rods at 12 percent to reach 5 feet: drop = 15 x 0.12 = 1.8 feet, and 5 / 1.8 = 2.8, so 3 rods and about 45 feet of run.

The bore calculator does this and also converts pitch from percent to degrees.

Rods for the whole shot

Total rods are the shot length divided by the rod length, rounded up. A 300 foot bore is 30 rods of 10 feet or 20 rods of 15 feet. The pilot goes out rod by rod, and the pullback takes the same rods back out, so the number is also how many you break out on the return.

A simple way to plan the shape, using the 200 foot, 6 feet deep example: 3 rods down at 20 percent (30 feet), 14 rods running level (140 feet), and 3 rods climbing back up (30 feet). That is 20 rods. Real shots wander, and a climb out usually needs to follow the same pitch limits as the dive, so treat this as a plan to check against the locator, not a promise.

Limits to remember

Drill rod only bends so far. A common limit is about 10 percent change of pitch per rod, so you cannot go from steep to level in one rod. The depth that matters to an inspector is the shallowest point of the bore, not the average, so plan and record that one.

Common questions

Does the surface run equal rod length times rods? Roughly, at gentle pitch. It is a planning number. Steeper pitch shortens the horizontal distance each rod covers.

What if the calculator says 2.8 rods? Round up to 3. You cannot load a partial rod, and you want to be at or past depth, not short of it.

Do I need to call 811 first? Yes, before the entry pit is set. Pothole the crossings so the depth you plan clears what is already down there.

Utility crews keep the bore log, depth of cover and locate tickets together on the job. TrackOver for utility contractors is built around that.

Related

More from the dirt world

TrackOver keeps the as-builts, markout tickets, hours, and job costs this page talks about. Start free, or see how it works.

Keep the job, the photos and the invoice in one place

TrackOver is job tracking for excavation, utility, paving, snow and lawn crews. Try everything free for 7 days.

  • No card to start
  • Cancel any time, no contract
  • Export your data whenever you want