Tolerance zone
How close can you dig to a marked utility?
It depends on the state. Most states set a tolerance zone around the mark, commonly 18 or 24 inches on each side, inside which you expose the line by hand or other approved gentle means before machine digging. Read your state's rule, not a number from another state.
A utility mark is the locator's best estimate, painted at the surface. It is not a surveyed line. States deal with that by drawing a zone around the mark and saying how you may dig inside it. That zone is the tolerance zone, and the number is not the same everywhere.
Why there is no one number
Dig-law is state law. Looking through the 811 rules by state, you will find zones written as 18 inches, 24 inches, 2 feet, and some that are measured from the outside edge of the facility instead of from the mark. At least one lets water and sewer operators choose a wider zone. Some states are not confirmed on our page at all, and say so. Do not use a number from the last state you worked in.
Each state has its own page from the 811 rules index, with the wording and where it comes from. Check the date on the page, and when it matters, confirm with your state's one-call center.
What the zone usually means for your dig
- It applies on both sides of the mark and along the whole length of the line.
- Inside it, many states require you to expose the line with hand tools or another approved non-destructive method before you use a machine. Whether vacuum excavation counts, and what else is allowed, is state-specific.
- Outside it, you can use machines, but marks are still approximate and the line is not exposed until you see it.
- Once a line is exposed, you can measure its real position and depth. Photograph it with a tape in the frame.
OSHA points the same direction in 29 CFR 1926.651(b): the estimated location of underground utilities has to be determined before you open an excavation, and when you approach them, their exact location has to be found by safe and acceptable means.
Worked example: crossing a marked line
This uses made-up zones so you can check the math. Your state's rule may say something different.
Suppose your state's zone is 24 inches on each side of the mark. A trench 3 feet wide crosses a marked line at a right angle and goes 5 feet deep.
- Hand-dig strip along the trench: 24 + 24 = 48 inches, which is 4 feet.
- Volume by hand: 4 x 3 x 5 = 60 cubic feet, or 60 / 27 = 2.2 bank yards.
Now suppose the rule is written as the width of the facility plus 18 inches on each side of its outer edge, and the marked line is a 6 inch pipe.
- Strip: 6 + 18 + 18 = 42 inches, which is 3.5 feet.
- Volume by hand: 3.5 x 3 x 5 = 52.5 cubic feet, or 1.9 bank yards.
Two different rules, two different strips, each a couple of yards by hand. If the line runs parallel to the trench instead of across it, the hand-dig strip runs the full length of the run, and that number gets large quickly. That is the reason to plan the offset before the trench is laid out, not after.
Practical habits
- Pothole early. Expose crossings ahead of the main dig so depth is known before you size the trench. See potholing and daylighting.
- Keep the marks alive. Do not dig inside the zone off faded paint. Photograph marks on day one.
- Hand-tool, then machine. Take the first lift by hand in the zone, then the bucket can take over outside it.
- Stop if it does not match. If you find a line where no mark said one was, or a different type than the color said, stop and call it in.
Common questions
Is the zone measured from the mark or from the pipe? It depends on the state. Some measure from the mark, others from the outside edge of the facility. The state page tells you which.
Can I use an excavator inside the zone? Many states say not until the line is exposed. Check your state's wording, and follow your competent person on site.
Is vacuum excavation allowed inside the zone? In many states it counts as a gentle method, but not all. Confirm in your state's rule.
Does the zone change if the line is deep? Depth does not shrink it. The mark is still an estimate of where the line sits sideways, and the line may be deeper than you expect, so expose it before you assume.
Excavation crews that keep the ticket, the mark photos and the pothole depths with the job have the record if a line gets questioned. TrackOver for excavation contractors keeps them in one place.