HDD bore cost per foot calculator

Enter what a day on the bore costs you, how many feet you bore a day and how many reamer passes it takes. See the cost per foot and the job total.

The bore
What it costs
$49.50
cost per foot
$49,500
job total
10
days billed
$4,600
cost of one day
$46.00
per foot before mobilization
3.3 + 4.4 + 2.2
pilot + reaming + pullback days
$59.40
per foot at your markup ($59,400)

Days = length / pilot feet a day + (passes + 1) x length / reamer feet a day, the extra one being the pullback. Cost = billed days x (rig + crew + fluid) + mobilization. Per foot = cost / length. Markup is a percent of your cost, not of the price: see the markup and margin calculator to work from a margin.

Every box is yours. The starting numbers are examples to show the math, not prices, rates or averages for any rig, crew or market.

More free calculators:

Turn this number into an estimate
TrackOver turns it into the estimate, the schedule and the invoice. 7-day free trial, no card needed.
Try TrackOver freeSee it first, no signup
How do you figure directional boring cost per foot? Add up what a day on the bore costs you: the rig, the crew and the drilling fluid. Work out the days the job takes: the pilot, each reamer pass and the pullback. Multiply the days by the day cost, add mobilization and demobilization, then divide by the bore length in feet.

When to use it

Use it when you are pricing a directional bore by the foot, checking a quote against your own costs, or seeing how passes and daily production change the number.

How to measure on site

  1. Add up a day: the rig and locating gear, the crew with payroll costs, and the fluid you mix and haul.
  2. Pull the feet you bored in a day from past daily logs in similar soil, for the pilot and for a reamer pass separately.
  3. Count the reamer passes the product size and ground call for, plus your cost to mobilize and demobilize.
Worked example (example figures only): 1,000 ft bore, 2 reamer passes
  • Day cost: $1,800 rig + $2,400 crew + $400 fluid = $4,600.
  • Pilot days: 1,000 ft / 300 ft a day = 3.3.
  • Reaming days: 2 passes x 1,000 ft / 450 ft a day = 4.4. Pullback days: 1,000 / 450 = 2.2.
  • Work days: 10. Billed as whole days: 10.
  • Bore cost: 10 billed days x $4,600 = $46,000. Plus $3,500 mobilization = $49,500.
  • Cost per foot: $49,500 / 1,000 ft = $49.50. With a 20% markup: $59,400, or $59.40 a foot.
  • Without rounding the days it is $49.50 a foot. The same bore at 300 ft costs $57.67 a foot, because the mobilization is spread over fewer feet.

Common questions

How do you figure directional boring cost per foot?

Add up what a day on the bore costs you: the rig, the crew and the drilling fluid. Work out the days the job takes: the pilot, each reamer pass and the pullback. Multiply the days by the day cost, add mobilization and demobilization, then divide by the bore length in feet.

What goes into the cost of a day?

The rig and locating gear, the crew's pay with payroll costs, and the drilling fluid, additives and disposal. Fuel, a vac truck or a trailer belong here too if they run every day. Type your own figures. This tool has no price book.

How many feet can a rig bore in a day?

It depends on the rig, the soil, the depth, the product size and the crew. Check your own daily logs from past bores in similar ground and use those. The starting numbers here are examples only.

How do reamer passes change the cost?

Every reamer pass is another trip down the full length of the bore, and the pullback is one more. Each one takes days of rig and crew time. A larger product or harder ground means more passes, so the cost per foot goes up with them.

Should I count whole days?

Usually yes. The rig and crew are on site for the full day even when the last pass ends at noon. Leave whole days on to charge a part day in full, or turn it off to see the plain math.

Where does mobilization go?

It is a cost for the whole job, so it is added once and then divided over the footage. A short bore carries the same mobilization as a long one, which is why short bores cost more per foot.

Is this the price I should quote?

No. It is your cost per foot. The markup line shows a price at the markup you type. Markup is a percent of cost and margin is a percent of price, so use the markup and margin calculator if you are working from a margin.

Pricing a bore?

TrackOver keeps the estimate, the crew schedule, the daily footage and the job costs in one place, from the first quote to the final invoice.

Try TrackOver free

7-day free trial, no card needed. See it in 2 minutes

Start your trial with your trade set up:

Want the details first? See how TrackOver runs the job for Fiber and Drilling & Boring.