OSHA trench sloping calculator

The simple-slope maximum for an open-cut trench by soil type, how wide it opens at the top, and when a protective system or an engineer's design is required.

The trench
Result
1½ : 1
max slope (run : rise), 33.7°
12 ft
lay-back each side
27 ft
width at the top
Over 5 ft deep: a protective system is required. Slope it back to the ratio above, or use a trench box or shoring.

These are the simple-slope maximums from OSHA 29 CFR 1926 Subpart P for excavations up to 20 ft, and they assume no standing water, no nearby surcharge load, and soil classified by a competent person. Benching and shielding are other allowed options. This is a planning aid, not a substitute for that on-site classification.

How deep can a trench be before it needs a protective system? OSHA requires a protective system in any trench 5 feet deep or more, unless the excavation is entirely in stable rock. Below 5 feet a system is not required by the depth rule, but a competent person can still call for one if they see a cave-in hazard. The three protective options are sloping the walls back, a trench box (shield), or shoring.

Common questions

How deep can a trench be before it needs a protective system?

OSHA requires a protective system in any trench 5 feet deep or more, unless the excavation is entirely in stable rock. Below 5 feet a system is not required by the depth rule, but a competent person can still call for one if they see a cave-in hazard. The three protective options are sloping the walls back, a trench box (shield), or shoring.

What is the maximum trench slope for each soil type?

For a simple slope up to 20 feet deep, the maximum allowable slopes are 3/4 to 1 for Type A (about 53 degrees from horizontal), 1 to 1 for Type B (45 degrees), and 1.5 to 1 for Type C (about 34 degrees). Stable rock can be vertical. Those ratios are horizontal run to vertical rise, so Type C lays back 1.5 feet for every foot of depth.

How do I know what soil type I have?

A competent person classifies it on site using at least one visual and one manual test. Type A is hard cohesive soil like stiff clay. Type B is medium, such as silt or clay that has been previously disturbed. Type C is the least stable: granular soils like sand and gravel, or any soil with water seeping in. When in doubt, classify to the weaker type, and remember layered or previously excavated ground is never Type A.

How wide does a sloped trench open at the top?

The top width is the trench bottom width plus the lay-back on each side, and each side lays back the slope ratio times the depth. A 6 foot deep trench with a 3 foot bottom in Type C soil lays back 9 feet per side, so it opens 21 feet wide at the surface. That is why deep sloped trenches need a lot of room and are often boxed or shored in tight corridors instead.

When does a trench need an engineer?

Once an excavation reaches 20 feet deep, the tabulated slopes no longer apply and the protective system must be designed by a registered professional engineer. Below that depth you can use OSHA's slope table, manufacturer's tabulated data for a shield or shoring, or an engineered design.