Mediacom won $122.4 million in BEAD grants to serve 17,793 locations in Georgia, Missouri, Indiana, Mississippi, Iowa, and Arizona, according to the state award lists below. These are wired builds, which means construction: placement, boring, splicing and drops.
Iowa
$100.4 million
Listed as Mediacom LLC · 11,124 locations · Fiber · provider match $60.4 million · est. completion October 31, 2028 · about 6,779 mi buried fiber (state estimate)
Source: Iowa Department of Management, Broadband Office: BEAD Final Proposal files (approved) (approved 2025-11-24)
Georgia
$12.7 million
Listed as Mediacom LLC · 2,513 locations · Fiber · provider match $12.9 million · est. completion January 1, 2030 · about 230 mi buried + 98 mi aerial fiber (state estimate)
Source: Georgia Technology Authority, BEAD Final Proposal data files as submitted (as submitted 2025-09-03)
Arizona
$5.8 million
Listed as Mediacom LLC · 3,375 locations · Fiber · provider match $10.3 million · est. completion December 15, 2028 · about 140 mi buried + 60 mi aerial fiber (state estimate)
Santa Cruz
Source: Arizona Commerce Authority, BEAD final proposal exhibits (subgrantees, deployment projects, locations and CAIs, 12/2/2025) (retrieved 2026-09-24)
Missouri
$1.8 million
219 locations · Cable (HFC) (60%) / Fiber (40%) · provider match $2.1 million · est. completion January 1, 2029 · about 43 mi buried + 8 mi aerial fiber (state estimate)
Source: Missouri Office of Broadband Development, BEAD Final Proposal data files (files posted 2025-09)
Indiana
$947,686
Listed as Mediacom LLC · 363 locations · Fiber · provider match $1.4 million · est. completion January 15, 2026 · about 26 mi buried + 5 mi aerial fiber (state estimate)
Source: Indiana Broadband Office, BEAD Final Proposal data uploads (files dated 2025-09-12)
Mississippi
$741,963
Listed as MEDIACOM LLC · 199 locations · Fiber · provider match $494,642 · est. completion December 31, 2028 · about 16 mi buried fiber (state estimate)
Source: Mississippi BEAM, BEAD Final Proposal Exhibits A-E (version approved by NIST) (NIST approved 2026-06-30)
BEAD grants
$122.4 million
Locations
17,793
Grant per location
$6,878
Fiber miles (est.)
7,234 buried · 171 aerial
Latest completion
January 1, 2030
What this build needs from crews
- Underground, about 7,234 miles. Directional boring, plowing or trenching, conduit and handholes, then restoration. Locates come first on every foot (utility locating).
- Aerial, about 171 miles. Make-ready, strand and lash, and pole attachments (aerial fiber), usually with traffic control on the road.
- Splicing and drops. Every one of the 17,793 locations needs a drop and a splice at the end (fiber splicing).
How subs usually get on a BEAD build
- Find out who is building. Providers often hand construction to a prime or an engineering and construction firm, and those firms hire the subs.
- Get your paperwork ready before you call: certificate of insurance, W-9, safety program, and proof you can do the footage.
- Ask what the state's BEAD rules mean for subs. Workforce, safety and reporting requirements vary by state and are often passed down.
- Be findable. List your crew with the states and trades you cover, and watch fiber work on the board.
Other wired BEAD winners in the same states
BellSouth Telecommunications (AT&T)MS · $224.6 millionWecomAZ · $195.8 millionStrategic ManagementIN · $149.7 millionNavajo NationAZ · $148.6 millionMainstream Fiber NetworksIN · $121.9 millionWindstream Georgia CommunicationsGA · $79.2 millionTec of JacksonMS · $57.0 millionSurf InternetIN · $55.0 million
Want to build for Mediacom?
Providers and their primes staff these builds with subcontractors. List your crew with the states and trades you cover so they can find you. Free.
Provisional awards can change as states finalize agreements. TrackOver isn't affiliated with Mediacom. All providers.