Mississippi BEAD funding
Mississippi's BEAD final proposal covers 93,283 locations. 79,288 of them (85.0%) are slated for fiber to the premises, which ranks Mississippi #11 of 51 for fiber locations. The deployment cost is $508.4 million against an original allocation of $1.20 billion.
Technology mix
| Fiber to the premises | 79,288 | 85.0% |
| Low earth orbit satellite | 13,474 | 14.4% |
| Hybrid fiber-coax (cable) | 521 | 0.6% |
Who won BEAD money in Mississippi
11 providers, largest grant first. The ones building fiber or cable are the ones hiring construction crews.
Source: Mississippi BEAM, BEAD Final Proposal Exhibits A-E (version approved by NIST) (NIST approved 2026-06-30). Summed per provider from the latest version Mississippi posts, approved by NIST on 2026-06-30. It totals $508,356,954.98 and 93,297 locations, $3,750 and 14 locations above NTIA's figures, which match the earlier NTIA-approved version exactly. Provisional awards can change as the state finalizes agreements.
What it means for contractors
Fiber locations are the ones that turn into construction: underground and aerial placement, boring, splicing, drops, and restoration. The providers that won these areas build them, often with subcontractors. Check the Mississippi broadband office's BEAD page for the providers selected in each area. Those providers, and the primes they hire, are who to call about sub work.
Fiber work in Mississippi on the board
No open fiber posts in Mississippi right now. Post work or list your crew, both free.
Fiber crews that work in Mississippi
Source: NTIA, final proposal overview updated January 28, 2026. NTIA marks these figures subject to change pending final review. All states.