Log a rain day and pay the minimum
Use this when the crew gets rained out. It shows the forecast for the next 7 days, logs the day, and works out the minimum hours you owe each person. Only owners and managers can use it, because it is pay.
1. Open Rain pay
On the Job Schedule, click Rain pay. It opens the Rain days page.
2. Set the minimum
Under Pay a minimum on rain days, type the hours each person is owed, like 4, and press Save. Leave it blank and rain days pay nothing. Time a person already clocked that day counts toward the minimum, so they are only topped up.
3. Check the week
Next 7 days shows the forecast and how many jobs are on each day. A day marked Rough day has rain, snow, storms or a 60% or higher chance of rain. On a day with jobs, press Rained out?, or Log as rain day on a rough day.
4. Log the day
Uncheck any job that still ran. Check the Rain-day hours owed for each person (they are filled in for you) and change them if needed, then press Log rain day. You can add a note too. The jobs are not moved, so push them to another day on the Job Schedule and tell the customers there.
5. Pay it out
Logged days are listed under Logged rain days. Press Download hours (CSV) to get who is owed what. Press Remove on a day you logged by mistake.
Pro tip: A day with no forecast still logs. The screen just shows No forecast next to it.