Skip to content

California BEAD funding

California's BEAD final proposal covers 270,571 locations. 143,098 of them (52.9%) are slated for fiber to the premises, which ranks California #3 of 51 for fiber locations. The deployment cost is $1.42 billion against an original allocation of $1.86 billion.

Allocation
$1.86 billion
Deployment cost
$1.42 billion
Locations
270,571
Fiber locations
143,098

Technology mix

Fiber to the premises143,09852.9%
Low earth orbit satellite72,93727.0%
Fixed wireless54,53620.2%

Who won BEAD money in California

20 providers, largest grant first. The ones building fiber or cable are the ones hiring construction crews.

29,366 locations · Fiber · provider match $247.3 million · est. completion June 1, 2030 · about 1,563 mi buried + 2,424 mi aerial fiber (state estimate)
47,680 locations · Fiber · provider match $382.2 million · est. completion June 1, 2030 · about 2,887 mi buried + 2,331 mi aerial fiber (state estimate)
21,785 locations · Fiber · provider match $58.6 million · est. completion June 1, 2030 · about 287 mi buried + 1,039 mi aerial fiber (state estimate)
7,762 locations · Fiber · provider match $27.1 million · est. completion June 1, 2030 · about 458 mi buried + 197 mi aerial fiber (state estimate)
17,762 locations · Fiber · provider match $40.9 million · est. completion June 1, 2030 · about 389 mi buried + 974 mi aerial fiber (state estimate)
3,943 locations · Fiber · provider match $19.3 million · est. completion June 1, 2030 · about 393 mi buried + 121 mi aerial fiber (state estimate)
49,705 locations · Satellite (LEO) · provider match $13.8 million · est. completion June 1, 2040
10,871 locations · Fiber · provider match $16.8 million · est. completion June 1, 2030 · about 1,160 mi buried fiber (state estimate)
47,321 locations · Licensed-by-rule fixed wireless · provider match $21.1 million · est. completion June 1, 2030
1,537 locations · Fiber (87%) / Licensed fixed wireless (13%) · provider match $3.3 million · est. completion June 1, 2030 · about 160 mi buried fiber (state estimate)
23,232 locations · Satellite (LEO) · provider match $19.8 million · est. completion June 1, 2040
1,710 locations · Unlicensed fixed wireless · provider match $4.1 million · est. completion June 1, 2030
353 locations · Licensed fixed wireless · provider match $611,150 · est. completion June 1, 2030 · about 10 mi buried fiber (state estimate)
2,427 locations · Fiber · provider match $2.1 million · est. completion June 1, 2030 · about 14 mi buried + 102 mi aerial fiber (state estimate)
613 locations · Unlicensed fixed wireless · provider match $1.0 million · est. completion June 1, 2030 · about 4 mi aerial fiber (state estimate)
3,050 locations · Unlicensed fixed wireless (66%) / Licensed-by-rule fixed wireless (34%) · provider match $590,045 · est. completion June 1, 2030
453 locations · Licensed-by-rule fixed wireless (76%) / Fiber (24%) · provider match $711,692 · est. completion June 1, 2030 · about 4 mi aerial fiber (state estimate)
60 locations · Fiber · provider match $372,798 · est. completion June 1, 2030 · about 3 mi buried + 8 mi aerial fiber (state estimate)
91 locations · Licensed-by-rule fixed wireless · provider match $146,574 · est. completion June 1, 2030
850 locations · Unlicensed fixed wireless · provider match $144,174 · est. completion June 1, 2030

Source: California Public Utilities Commission, Resolution T-17920 (Rev. 1) Final Proposal appendices B1-B5 (Resolution T-17920 Rev. 1 files, 2026-07-21). Summed per provider from the data attachments to CPUC Resolution T-17920 Rev. 1, which revises California's Final Proposal after NTIA approved it in July 2026. Grants total $1,415,047,584.78 and locations 270,571, matching NTIA's approved figures exactly. As of this pull the CPUC had not posted a final vote on the resolution. The larger set the CPUC submitted in December 2025 is not used. Provisional awards can change as the state finalizes agreements.

What it means for contractors

Fiber locations are the ones that turn into construction: underground and aerial placement, boring, splicing, drops, and restoration. The providers that won these areas build them, often with subcontractors. Check the California broadband office's BEAD page for the providers selected in each area. Those providers, and the primes they hire, are who to call about sub work.

California BEAD officeNTIA state pageFinal proposal overview (PDF)California 811 rules

Fiber work in California on the board

No open fiber posts in California right now. Post work or list your crew, both free.

Source: NTIA, final proposal overview updated July 17, 2026. NTIA marks these figures subject to change pending final review. All states.